A nickel mine can move a great deal of rock without producing the same weight of nickel. To compare countries, start with how much nickel the mined material contains, then look at the deposits that supply it.
Indonesia led estimated nickel mine production in 2025 at 2.6 million metric tons of contained nickel, according to the U.S. Geological Survey. The Philippines followed at 270,000 metric tons and Russia at 200,000. The ranking measures nickel in mined material, not tonnes of ore moved, refined metal made, or reserves still in the ground.
How to use this article: Start with the 2025 table, check the ore-grade calculation, or compare the Indonesian, Canadian and Russian deposit examples.
The 2025 nickel mine-output ranking
This ranking uses the 2025 estimate column in the USGS Mineral Commodity Summaries 2026 nickel chapter. It includes all nine individually named mine-production reporting areas. New Caledonia is a French territory reported separately by USGS, not a sovereign state or a combined France total. The grouped “Other countries” entry is part of world production, but it cannot be ranked as one producer.
Named mine-producing areas
| 2025 rank | Reporting area | 2025 estimate | 2024 in same edition |
|---|---|---|---|
| 1 | Indonesia | 2,600,000 | 2,310,000 |
| 2 | Philippines | 270,000 | 354,000 |
| 3 | Russia | 200,000 | 205,000 |
| 4 | Canada | 140,000 | 125,000 |
| 4 | New Caledonia | 140,000 | 116,000 |
| 6 | China | 120,000 | 115,000 (estimated) |
| 7 | Brazil | 70,000 | 67,500 |
| 8 | Australia | 45,000 | 98,000 |
| 9 | United States | 10,000 | 7,490 |
Canada and New Caledonia each display 140,000 metric tons in 2025. That is a shared rank at the source’s published precision, not evidence that actual output matched exactly. The USGS notes that it substantially revised Canada’s 2024 production in this edition based on a government report; use that edition’s 2024 column if comparing the two years.

Why ore weight, refining and reserves are separate
A simple contained-nickel calculation
Consider 100,000 metric tons of ore on the same weight basis as the grade measurement. At 1.5% nickel by mass, it contains 1,500 metric tons of nickel: 100,000 × 0.015 = 1,500. That is a hypothetical ore-grade example, not an operating figure for any mine. Recovery losses and processing choices mean the mine’s contained nickel is not a promise of 1,500 metric tons of refined metal.
Refinery output records a later production stage. Concentrate or other nickel-bearing intermediate products can cross a border before they are processed. In 2025, for example, USGS describes Michigan’s Eagle Mine producing about 10,000 metric tons of nickel in concentrate and shipping it to smelters in Canada and elsewhere. That mine output belongs in the U.S. row even though smelting took place abroad.
Reserves answer a different question again: they describe the economically recoverable portion of identified material under the assessment’s conditions. They are a stock, while annual mine production is a flow. Do not rank the 2025 mine output by the reserves column or add smelter output to mined nickel: doing so would mix unlike figures and could count the same material twice.
How laterites and sulfides shape the map
Laterite weathering versus magmatic sulfides
Laterites form when exposed magnesium- and iron-rich rocks weather over long periods. In warm, wet settings, weathering and drainage can enrich nickel in layers above less-altered bedrock. Indonesia’s geological agency identifies lateritic nickel associated with ultramafic rocks in southeastern Sulawesi and southeastern Halmahera. The islands’ locations are clearer in our Indonesia geography profile. They are examples of why the national total reflects particular geological districts, not the whole archipelago equally.
Magmatic sulfides form through a different process. Nickel can concentrate with sulfur and copper as molten rock evolves and cools. USGS describes sulfide deposits at the margin of an impact-generated igneous complex in Ontario’s Sudbury district, and around mafic intrusions at Norilsk–Talnakh in Siberia. These examples show why the map of nickel mining reaches far beyond tropical laterite districts. A country can host more than one deposit type; the production table does not allocate every ton by geology.
Sorowako, Sulawesi: Vale mines saprolitic nickel laterite there and smelts the ore to make nickel matte. Saprolite forms as ultramafic rock weathers in place; this is one actual laterite process, not the route used at every site.
Sudbury, Ontario: Nickel occurs in sulfide ores around the margin of the igneous complex. The Copper Cliff smelter handles nickel concentrates and produces an intermediate matte. Unlike the Sorowako example, concentration precedes smelting; neither intermediate is automatically a battery-grade product.
How to recreate the ranking
Use only the 2025 estimated mine-production values in the nickel chapter’s “World Mine Production and Reserves” table. Keep the nine named reporting areas; exclude the grouped and world rows. Sort descending on the displayed tonnages and give equal values the same rank, skipping the occupied position after a tie. A missing or withheld value is not zero. In particular, the USGS marks U.S. refinery byproduct figures with W (withheld to avoid disclosing proprietary data). That does not change the published mine figure.
For Indonesia’s global share, divide 2,600,000 by the separately reported rounded world estimate of 3,900,000. The result is about 66.7%, or two-thirds. Do not rebuild the world total by summing only named rows, and do not infer an exact global total from the rounded figures.
Frequently Asked Questions
Does an unreported value mean no nickel was mined?
No. The summary has a grouped “Other countries” entry for mine output and does not give a separate mine figure for every producer. Leave unreported entries unranked unless a comparable source supplies the missing detail.
Can a laterite mine supply battery-grade material?
It can feed a processing route that makes a suitable intermediate, but “laterite” describes a rock deposit, not the purity of the final product. The mine figure alone cannot tell you how much met a battery supply chain’s specifications.
Does the largest reserve number identify the next production leader?
No. Converting a reserve into future production depends on projects, recovery, investment, permitting, operating conditions and demand. Reserves and mine output answer different questions at different times.
What Did We Learn Today?
Read a nickel ranking in order: check what was counted, whether the figures are estimates, and which reporting areas were made visible. Then look to the deposit geography to understand why distant regions can mine the same metal from very different rocks.
Sources & Data Notes
Open sources & methodology
The ranking counts the nickel content of mine output in the February 2026 USGS edition’s 2025 column. New Caledonia is a separate published reporting area; grouped and rounded total rows are excluded from ranking.
- USGS: Mineral Commodity Summaries 2026, nickel chapter, mine production, refinery figures, flags and reserve definitions.
- USGS: Nickel-cobalt laterites deposit model and USGS: Magmatic sulfide deposit model, including Sudbury and Norilsk–Talnakh.
- Indonesia Geological Agency: Minerals Yearbook 2024, regional laterite geology.
- Operating examples: Vale Indonesia, Sorowako saprolite and nickel matte; Vale, Copper Cliff Smelter Complex process description.
- Natural Earth: 1:10m reference boundaries; map locations identify ranked reporting areas, not deposits or jurisdictions.